December 7, 2006 -
Groundbreaking |
|
On a cold and windy December 7, 2006, ground
is broken for the expansion of the Ysleta Branch Library. |
 |
Showing some
expertise with a shovel are (foreground to back) Carol Brey-Casiano -
Library Director, Tom Moorhead - Ysleta Branch Manager, Ivonne Jimenez -
Deputy Director of Library Services, Luis Chapparro - Vice-President of
the El Paso Public Library Board, Judith Luevano, of the office of
Representative Eddie Holguin, Carlos Armendariz - President of the El
Paso Public Library Board, and Guillermo Barajas - Architect. |
|
|
|
December 29, 2006 |
January 11, 2007 |
January 18, 2007 |
|

Rough-in for the plumbing after back filling
the foundation hole seen in the ground breaking photo above. |

Foundation preparation |

Foundation concrete pour from |
|
|
February 8, 2007 |
February 20, 2007 |
|

Structural steel and interior walls
partially completed |
 |
Construction of your expansion project is
right on time! Most of the structural steel is up and the interior walls
are framed. The electrician is making good progress and we’ll see some
of the other trades as soon as the roof is done. Come have a look! |
|
|
March 16, 2007 |
|
|
|
April 17, 2007 |
|
|
|
April 19, 2007 |
|
|
|
May 1, 2007 |
 |
Door leading to the new expansion. Located
between computer lab and Children's area. |
|
|
|
June 2, 2007 |
|
|
|
June 19, 2007 |
 |
Construction is “substantially
complete”! Some interior finishing remains but we hope to be
open to the public in August, with a grant opening date to be
announced at a later date. |
|
|
|
|
|
|
|
|
|
|
|